background image
FENWICK ISLAND ­ Distress
has been relieved in Fenwick Island
as the Army Corps of Engineers
completed the beach replenishment
project last week.
"I know the project caused a little
bit of heartache in town but overall,
and I think town staff will agree with
me, it went off without a hitch. We
still received a lot of inquiries and
complaints, but once again the proj-
ect was not set by the town," Town
Manager Merritt Burke said during
last Friday's Town Council meeting.
"I want to give a lot of credit to Capt.
[Tim] Ferry and the lifeguards for
consistent posting of information,
specifically photos on Twitter and
Facebook. I would like to believe we
set the standard for the rest of the
beach communities moving forward
using social media."
There were no problems encoun-
tered, Ferry confirmed on Friday.
"It ended up being a very, very
good working relationship with [con-
tractor] Great Lakes keeping us up
to date on the movement of their
areas and keeping as much beach
open as possible down there," Ferry
said. "I don't think at any point in
time there was one beach crossover
that was closed during the whole
process. There was access 100
percent of the time. You might have
had to walk a little bit north or south
to get to a particular beach but
things worked very well with that."
The project began on July 26 and
the town announced the project had
been completed in Fenwick on Aug.
21. There were three subline pipes
dropped between Atlantic and
Houston streets and the contractor,
Great Lakes Dredge and Dock,
worked in four phases pumping
sand south of each pipe first as far
as the Maryland State Line and then
north to meet where they left off in
the previous phase until they had
reached the end of Fenwick on the
North end.
In South Bethany, roughly
476,000 cubic yards of sand will be
pumped onto the beach, while
Dewey and Rehoboth will get a
combined 455,000 cubic yards.
Overall, from New York to Virginia,
an estimated 26 million cubic yards
of sand will be pumped onto the
beaches at an estimated cost of
$600 million.
The contract duration will be
approximately 210 days from start
to finish and the wide cost range for
the project is estimated at anywhere
from $10 million to $25 million.
Fenwick Beach Pumping Completed
Page 26
August 30, 2013
The Dispatch/Maryland Coast Dispatch
By JOANNE SHRINER
STAFF WRITER
Project Moves North Along Del. Coast